curve-left home-curve-left

Explore the approvals and applications for the Liverpool Range Wind Farm.

Approvals

The Project received planning approval for up to 267 turbines from the Minister of Planning, NSW in March 2018. A copy of the final approval and conditions can be downloaded below.

You can also visit the Project page on the NSW Major Projects website, here.

The Project also received approval under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) issued by the Department of the Environment and Energy in June 2018 (reference EPBC 2014/7136), and can be downloaded below.

Applications

The Environmental Assessment (EA) for the Liverpool Range Wind Farm was lodged with the NSW Department of Planning and Environment (DPE) in July 2014, and can be downloaded below.

A Response to Submissions report was lodged with DPE, which was placed on public exhibition from 1 August 2014 to 1 October 2014. A copy of the RTS can be downloaded below.

In September 2022 a Modification Application was submitted to DPHI for the Liverpool Range Wind Farm (Mod-1 Project). In response to submissions (RTS) received during the public exhibition period for the Modification Application, we have since made a number of changes and refinements to the Project. For example, the number of turbines proposed has been reduced to 185. These changes are reflected in the Mod-1 Application – Amendment Report (RTS Project) which was lodged in August 2023.

Due to an identified shortage of suitably skilled workforce and rental accommodation in the local region, and in response to government and community feedback, in October 2023 we further amended the Modification Application to include a Temporary Workforce Accommodation (TWA) Facility approximately 3 km from Coolah. This proposed amendment to the Project is described in the Mod-1 Application – Amendment Report TWA Facility.

Submissions reports have also been prepared for both the above amendments, to respond to community and government submissions regarding the proposed amendments.

The RTS Report, amendment reports, submissions reports and all updated environmental impact assessments have been submitted to DPHI and are available to view on the NSW Major Projects portal. These reports detail the consultation completed to-date, how submissions received during both public exhibition periods have been addressed, and clearly show the changes to the design and layout of the Project, including ancillary infrastructure.

DPHI will now review the documentation and make a determination on the Modification Application.

CLICK HERE to find out more about the RTS Project.

In June 2018, the Liverpool Range Wind Farm was approved by the Commonwealth Department of the Environment and Energy under Section 130(1) and 133 of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) (EPBC reference number 2014/7136).

Due to the changes to the design and layout associated with the Modification Application (described above), the Approved Action was re-referred to Department of Climate Change, Energy, the Environment and Water (DCCEEW) on 2 March 2023 (EPBC reference number 2022/09416).

The Minister determined on 30 March 2023 that the Project is considered a ‘controlled action’ under the EPBC Act, and that approval is required due to the potential for significant impacts on the following matters of national environmental significance (MNES), protected under Part 3 of the EPBC Act:

  • listed threatened species and communities
  • listed migratory species

On the same date, the delegate of the Minister determined that the Project be assessed by a Public Environment Report (PER). Final PER Guidelines for the assessment process were issued by DCCEEW on 31 July 2023.

The Public Environment Report is currently being finalised in consultation with DCCEEW and will be publicly exhibited once finalised.

We will keep the community informed as this process progresses, including updates on the timeframes, via our website, shopfront, newsletters and advertisements.