Salt Creek Wind Farm is currently under construction near Woorndoo, around 250 kilometres west of Melbourne, in the state of Victoria, Australia. The site is located on a Merino Stud Farm and offers excellent wind resource. Financial close for the project was received on June 30, 2017 and construction began in July 2017.

Planning approval for the project was obtained in 2007. The current permit allows construction of up to 15 turbines, producing up to 172 GWh of electricity per year, enough to power around 30,000 homes. Construction will take 12 months.

A Community Information Day was held on Tuesday, July 11, at the Woorndoo Recreation Reserve Social Rooms. For more information call 1800 122 823

View the Salt Creek Wind Farm Fact Sheet

Project News

Visit this page regularly to ensure you receive all news updates and promotional material related to the Salt Creek Wind Farm.

Community

We are a power company that believes in being involved in the communities where we operate and in the places where those communities live, work, bring up their children and run businesses. We implement a variety of initiatives to benefit communities in project areas.

Our Lend A Hand Foundation operates at four project sites, including Snowtown in South Australia. The Foundation assists small charitable organisations and individuals by giving them a hand when they need it most, through funding, mentoring and the provision of goods and services.
 

Services

Tilt Renewables will continue to recommend maximising local employment in our construction contracts. The majority of local employment is during construction, but the operations phase also provides opportunities for local employment and local business contracts. Typical goods and services likely to be sourced locally include accommodation, engineering, freight services, construction materials and equipment, local labour, technical contractors, earthworks services, fencing and landscaping.
 

Goods & Services Register

Tilt Renewables is committed to using local labour whenever possible. As we progress towards this financial close in Q1 of 2017 we are seeking expressions of interest from locals with expertise in a range of fields.

To register interest in providing goods or services for the project, please click here.
 

Media Releases

30 June 2017 - MEDIA RELEASE - Green Light for Salt Creek Wind Farm
 

Newsletters

Newsletters are an important part of Tilt’s community engagement and will increase in frequency as the Project develops.

To subscribe to our newsletter mailing list, please click here.

Download November 2017 newsletter

Download May 2017 newsletter

Download November 2016 newsletter  

Project Details

Location:
5km south of Woorndoo, Victoria

Wind Farm Layout

Transmission Line Route Plan

Transmission Line Pole Locations

Detailed transmission line map

Max Capacity:
Up to 54 MW

Annual Output:
Up to 172 GWh/year

Employment:
Circa 100 construction jobs, up to 4 full time staff post construction

Construction:
12 month project

Investment:
Circa $100 million


 

Contact Us

For more information please contact the project team:

Site Manager
Jason Donohue
0427 764 825

Tilt Renewables Project Manager